Congratulations on the Successful Completion of the Hot Tapping Connection Operation of Our Company's

2018-11-02

The Juye Distribution Station Heze Kunpeng Distribution Branch Transformation Project involves adding a Heze Kunpeng gas supply branch in the Juye Distribution Station of the Pingtai Branch Line to supply gas to the downstream Juye Kunpeng Gas Gate Station. The final gas transmission scale for sales is 1.0×108Nm3/a.

Since the project started, Wang Qinghu, the project manager, has led the EPC project department personnel including Dang Changle, Ren Weike, Huang Wenqiang, as well as the civil engineering and process installation construction teams to work steadily and make overall arrangements. While ensuring the construction quality, they completed all installation work in only 60 days and met the conditions for hot tapping connection operation.

1752546600383183.png

On October 31, 2018, leaders including Si Jingrui, Deputy General Manager of Production of Heze Kunpeng (the construction unit), Yang Yongchao, Chief of the Production Section of Zhongyuan Oil and Gas Transmission Branch, Meng Ye, Secretary of Zhongyuan Maintenance and Emergency Repair, Liu Changliang, Secretary of Heze Operation Area, and Sun Jian, General Manager of Beijing Oriental Huazhi Engineering Branch, visited the site to direct the hot tapping operation. In the morning, after Section Chief Yang of the Production Section issued the order to start the hot tapping operation, processes such as nitrogen replacement, testing, cutting of the original pipeline, and assembly of the connected pipeline were carried out in an orderly manner. By 15:30 p.m., a total of 5 hot tapping points and 13 welds on the site were all completed. Subsequent weld testing by the testing unit showed that all welds were qualified.

 1752546661124183.png

Thus, the hot tapping connection operation of the Juye Distribution Station Heze Kunpeng Distribution Branch Transformation Project was successfully completed and is now ready for commissioning and operation.

 1752546690890098.png

This project is the fourth EPC hot tapping connection task successfully completed by our company in 2018. The smooth completion of this hot tapping operation has also successfully won the unanimous recognition of Heze CNPC Kunpeng Natural Gas Utilization Co., Ltd., Zhongyuan Oil and Gas Transmission Branch, and Heze Operation Area for the construction capacity of our company's EPC projects! Congratulations to all members who have participated in the project. We hope you will continue to make great achievements in Huazhi's engineering projects!